ACO
Installation
ACO References Register
Education
Home         

An installed ACO Drain System should incorporate the following:
Correct grate type
Correct channel type and size
Minimum grade 4,000psi compressive strength cement concrete surround

Channel units are installed in a continuous trench, and are fully encased with concrete.

 

1. Excavation
Excavate trench to accommodate trench drain system. Excavation should be made around the center line.

 

Excavation must be sufficient enough to accommodate each of the following:

     i  Channel/catch basin width and depth dimensions.

    ii  Concrete surround dimensions - a minimum of 4” (Load Class A) of concrete on all sides, allow 6” for FlowDrain

        products to accommodate installation brackets. Specific loading and ground conditions will increase excavation size.

   iii  For sloped systems, excavate base to roughly follow fall of trench drain run.

 

Ensure all loose material is removed and base is compacted.

 

Run string line and laser level at finished surface level along full length of excavation to ensure trench is installed at correct grade.

 

2. Layout and outlet installation
All installations should start from the outlet point. For sloped trench systems, polymer concrete catch basin drill-outs match every 5th channel unit.

i
Determine type of outlet required and its position
ii
Install the outlet channel/catch basin and set haunch
iii
Select the numbered sloping channel units in order from deepest (highest channel number) to shallowest
iv
Install channels working away from the outlet
 

If fabrications are required, click here for instructions.

3. Trench drain installation
Channel units need to be supported at correct height and held securely in place to avoid movement during concrete pour.

There are a number of options available to support channel units.

a. Polymer concrete products
For new construction use either patty supports or installation devices.
For retrofit into an existing slab, channels can be hung from existing slab.
For detailed installation instructions for polymer concrete channels,
click here

Patty supports
Care should be taken that concrete is not trapped in joint between channels.

Channel Clamp
Channel clamp holds channel joints, and rebar allows height adjustment

and leveling.

Channel Hanger
2x4 slides through pocket at top of hanger. Hanger fits into locking bar recess on channel.
 

A number of installation aids are available, see Accessories for details.


b. Fiberglass products
These products have installation devices attached to frames to allow trench to be held in position by No. 4 or 5 rebar. FG200 can also be hung from grate locking.

For detailed installation instructions for fiberglass channels, click here

 


4. Channel bracing

To prevent the channel wall and joints being distorted by

the pressure of concrete, grates (or plywood cut to a snug

fit) should be installed in the channel.

 

 

 

 

 

 

The grates should be suitably wrapped to protect from concrete splash. Shims or washers placed along each side allow easy removal of the grating.

 

Fiberglass products are supplied with foam blocks to brace channel walls to prevent distortion.

 

 


5. Concrete pour
Concrete should have minimum 3,000 psi compressive strength.

Concrete should be poured evenly (both sides of channel) and carefully to avoid dislodging channels. A wand type vibrator should be used to ensure concrete distributes evenly underneath and around channels.

6. Pavement finishing
The top of the adjacent pavement must be above the grating level by approximately 1/8" (3 mm).

Brick pavers should be set slightly above the trench edge. First brick course should be set on mortar/concrete.

Care should be taken with asphalt rolling machines to avoid damage to trench edge.

7. Completing trench installation
i

Remove grates and remove protective wrapping.

ii
Remove debris from trench drain and make sure outlet pipes are clear.
iii
Install trash buckets in catch basins, if required.
iv
Flush trench run to check for pipe work blockages. Unblock if necessary.
v

Empty trash buckets and clean out pipe connections, if necessary. Re-install trash buckets.

vi

Re-install grates in proper position ensuring they are securely locked down.

The trench drain is now ready for use.

Maintenance

Regular inspections of the trench drain are recommended. Frequency will depend on local conditions and environment, but should be at least annually.

 

Inspections should cover:

Grates and locking devices

Catch basins and trash buckets

Concrete surround and adjacent paving

 

All items should be inspected for damage,  blockage or movement. Compare with site drawings if necessary.

 

Maintenance Guidelines:

i

Remove grates

ii
Remove debris from channel - a 4” shovel head is available (Part # 01315)
iii
Flush channels with water or high pressure washer (do not use boiling water or aggressive cleaning agents)
iv
Repair damaged surfaces where necessary with an appropriate ACO repair kit
v

Renew joint seals as required

vi

Empty trash buckets and clean out pipe connections, if necessary. Re-install trash buckets.

vii

Re-install grates in proper position ensuring they are securely back in place

 

| Home | About Us | Local Sales Support | Contact | Sitemap |

© ACO USA 2007